Central Stormwater Pipelines Project, Cambridge

Central Stormwater Pipelines Project

Waipa District Council
2022 to 2024

MaCC was the lead civil engineering consultancy for this ~$10M stormwater pipeline upgrade project west of Cambridge.

Our team led the project management, construction procurement, and was lead engineers on site during construction.

Construction included challenges of stormwater civil construction through busy sections of road, coordination with other services, working with large 1.8m diameter PE lined pipes, groundwater flows, and steep sections of earthworks.

The construction contract was delivered successfully in a collaborative working arrangement with the Contractor, developer, and Council. The works were delivered in advance of key programme dates and were within agreed budgets.

Central Stormwater Pipelines Project, Cambridge
Waipa District Council: Central Stormwater Pipelines Project, Cambridge.

Below are more examples of our work.

  • MaCC Bridleways Estate Cambridge
    Bridleways Estate Development, Cambridge

  • Taheke Geothermal Development Civil Design
    Taheke Geothermal Development

  • Kopaki Slip Retreat, Waitomo

  • Waikawa Bay Culvert Repair Project
    Waikawa Bay Culvert Repair Project

  • Kaueranga Road, Outlook 76 Landslip
    Kaueranga Road, Outlook 76 Landslip

  • Haultain Street Upgrade, Waipa
    Haultain Street Upgrade, Waipa